# POLO-ECO plus Premium bridge drainage

Pipes and fittings are connected with Top-Connect push-fit sockets, with no welding or solvent cement on site. Taking full flow, wind load and UV exposure into account, the general rule is a maximum support spacing of 300 cm:

| Pipe DN | Support spacing at full load (drainage), cm | Support spacing at partial load (e.g. cable conduit), cm |
| --- | --- | --- |
| 110–125 | 150 | 150–200 \* |
| 160 | 200 | 200–250 \* |
| 250 | 250 | 300 \* |
| 315–630 | 300 | 300 |

\* Longer spacings depend on the actual weight of the line.

Fixed points can be placed up to 12 m apart. Prefabricated support and suspension points avoid drilling or welding of fastenings later. For inspection and cleaning, the POLO-EHP Control cleaning pipe is available from DN/OD 110 to DN/OD 500.

Water from a bridge deck usually needs treatment before it reaches a watercourse. Vesmaco combines the pipe system with [stormwater treatment](https://vesmaco.eu/stormwater-treatment/) equipment and, where the outflow has to be retained, with [storage tanks](https://vesmaco.eu/storage-tanks/). Send us the drawings, diameters, lengths and schedule, and we will propose a POLOPLAST solution with a material list.